Collaborative
Training Consultants
102
Lake Hills Road, Tullahoma, TN 37388
Phone
931-454-2323
Cellular
931-247-4647
email
peteroot@ctc-usa.net
We provide
complete documentation of every Partnering Workshop, and provide a copy
for each Participant. This allows everyone to have a common
record of the session, which is prepared by Pete Root as the Project
Neutral. The minutes do not have a parochial bias of any
participating organization.
TABLE ROCK AND NORTH SALUDA FILTRATION PROJECT
INITIAL CONSTRUCTION PARTNERING WORKSHOP
January 28-29, 1997
MEETING MINUTES
RANDY ASHBURN ISTJ
PROJECT ENGINEER
BLACK AND VEATCH
8604 CLIFF CAMERON DR, STE 164
CHARLOTTE, NC 28269
704-548-8461 FAX 8640
ashburnrd@bv.com |
LARS BALCK INTP
VICE PRESIDENT
THE CROM CORP
PO BOX 1838
DAVIDSON, NC 28036
704-892-4629 FAX 4003
cromtank@bellsouth.net |
DAN BYERS, JR ISTJ
PROJECT MANAGER
GOOD WATER INC
PO BOX 16719
GREENVILLE, SC 29606
864-277-8503 FAX 2720
goodwater@mindspring.com |
TONY J CALLAHAN INTJ
PROJECT MANAGER
IVESTER, INC
PO BOX 8794
GREENVILLE, SC 29604
864-295-9970 FAX 9975 |
SCOTT DEWHIRST ESTP
STAFF ENGR
BLACK & VEATCH
545 N PLEASANTBURG DR, STE 101
GREENVILLE, SC 29607
864-232-6432 FAX 235-7704
dewhirstws@bv.com |
CAM FERGUSON ISTJ
MGR OF WATER RESOURCES
GREENVILLE WATER SYS
PO BOX 687
GREENVILLE, SC 29602
964-834-3742 FAX 5414 |
JACK ELMORE ISFJ
PROJECT MANAGER
MARK HENDERSON, INC
5322 SNAPFINGER PARK DR
DECATUR, GA 30035
770-987-6780 FAX 6783 |
DEAN de FREITAS ISTJ
SR PROJECT MANAGER
BEERS CONSTRUCTION
70 ELLIS ST NE
ATLANTA, GA 30303
864-297-9700
ddefreit@beerscc.com |
RICK GALWAY ISTJ
VICE PRESIDENT
GOOD WATER INC
PO BOX 16719
GREENVILLE, SC 29606
864-277-8503 FAX 2720
goodwater@mindspring.com |
TIM HALLIGAN
PRESIDENT
MORGAN CORP
PO BOX 3555
SPARTENBURG, SC 29304
864-433-8800 FAX 8808 |
PAUL HARGETTE ISTJ
PROJECT ENGR
BLACK & VEATCH
545 N PLEASANTBURG DR, STE 101
GREENVILLE, SC 29607
864-232-6432 FAX 235-7704
hargetteph@bv.com |
MICHAEL P. HOLT INTP
GROUP PRESIDENT
BEERS CONSTRUCTION
70 ELLIS ST
ATLANTA, GA 30303
404-659-1970 FAX 656-1575
mholt@beercc.com |
MIKE HORSLEY INTJ
TECHNICAL DIR FOR DESIGN
BLACK & VEATCH
8400 WARD PKWY
KANSAS CITY, MO 64114
913-458-3197 FAX 3730
horsleymb@bv.com |
BILL JACKSON ESTJ
SR PROJECT MANAGER
MORTENSON/HAILEY
PO BOX 923
TRAVELERS REST, SC 29690
864-834-3699 FAX 3799
bill.jackson@mortenson.com |
DOUG KINARD ISTP
SECTION MANAGER
SC DHEC
BUREAU OF WATER
2600 BULL ST
COLUMBIA, SC 29201
803-734-5364 FAX 4661 |
DAVID LYTLE ISTJ
PRESIDENT
SPECTROL INC
4760 HAMMERMILL RD, STE 204
TUCKER, GA 30084
770-939-3354 FAX 3556 |
BRYANT NIXON ISTJ
ASST PROJECT MANAGER
GOOD WATER INC
PO BOX 16719
GREENVILLE, SC 29606
864-277-8503 FAX 2720
goodwater@mindspring.com |
PAUL O’BRIEN INTP
PROJECT ENGINEER
MORTENSON/HAILEY
PO BOX 923
TRAVELER’S REST, SC 29690
864-834-3699 FAX 3799
p.o’brien@mortenson.com |
ANDY PETKASH INTJ
SENIOR PARTNER
BLACK & VEATCH
8604 CLIFF CAMERON DR, STE 164
CHARLOTTE, NC 28269
704-548-8461 FAX 8640
petkashav@bv.com |
VARDRY RAMSEUR
COMMISSIONER
GREENVILLE WATER SYS
2 EXCHANGE ST
GREENVILLE, SC 29605
864-277-3152 FAX 6766 |
MIKE SHARPLESS ISTJ
PROGRAM MANAGER
GREENVILLE WATER SYS
PO BOX 687
GREENVILLE, SC 29602
864-241-6007 FAX 6035
103226.2453@compuserve.com |
JOHN G. SNITZMIER ENTJ
SR RESIDENT PROJ ENGR
BLACK & VEATCH
46 PLEASANT RETREAT RD
TRAVELERS REST, SC 29690
864-834-2800 FAX 5885
snitzmierjg@bv.com |
LYNN STOVALL INTP
GENERAL MANAGER
GREENVILLE WATER SYS
PO BOX 687
GREENVILLE, SC 29602
864-241-6004 FAX 6035
lstovall@globalvision.net |
GARY TALMAGE ISTJ
SR PROJECT MGR
BLACK & VEATCH
8604 CLIFF CAMERON DR, STE 164
CHARLOTTE, NC 28269
704-548-8461 FAC 8640
talmagegr@bv.com |
PETE ROOT ISTP
PRINCIPAL/FACILITATOR
CTC
102 LAKE HILLS ROAD
TULLAHOMA, TN 37388
931-393-2335 FAX 454-9796
peteroot@ctc-usa.net |
DAVE VAN HOUT ISFJ
COST/SCHEDULE ENGR
MORTENSON/HAILEY
PO BOX 923, 36 PLEASANT RETREAT RD
TRAVELERS REST, SC 29690
864-834-3699 FAX 3799 |
DANIEL VERTANEN ISTP
VICE PRESIDENT
MORTENSON/HAILEY
PO BOX 710
MINNEAPOLIS, MN 55440
612-522-2100, X 541, FAX 1237
dan.vertanen@mortenson.com |
CHRIS WHALEN ISTP
ELECTRICAL SUPT
SPECTROL INC
4760 HAMMERMILL RD
TUCKER, GA 30084
770-939-3354 FAX 3556 |
JR WIESE ISTP
SUPERINTENDENT
MORTENSON/HAILEY
36 PLEASANE RETREAT RD
TRAVELERS REST, SC 29690
864-834-3699 FAX 3799
jr.wiese@mortneson.com |
BRAD WILLIAMS INTP
PROJECT ENGR
SPECTROL INC
4760 HAMMERMILL RD, STE 204
TUCKER, GA 30084
770-939-3354 FAX 3356 |
THOMAS WILSON ISTJ
SUPERINTENDENT
BEERS CONSTRUCTION CO
2582 RIVER RD
DALTON, GA
706-259-5115 FAX 5119 |
TONY WINIG ESTJ
MECH & ELECT COORD
MORTENSON/HAILEY
PO BOX 923
TRAVELERS REST, SC 29690
864-834-3699 FAX 3799 |
|
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
WORKSHOP
EXPECTATIONS
(LISTED BY PARTICIPANTS)
|
- TO ACCOMPLISH:
- BETTER LISTENING SKILLS
- BETTER ABLE TO EXPRESS VIEWS WITHOUT BEING
TOO AGGRESSIVE/TOO DEFENSIVE
- SEE HOW PERSONAL OUTLOOK COLORS PERCEPTIONS
- RESULTS:
- LESS FRUSTRATION WITH NEBULOUS SPECS AND
CONTRACT
LANGUAGE
- LESS TIME "CHECKING" CONTRACTORS
- MORE THOROUGH STARTUP PLAN/EXECUTION
- LONG-TERM PROFESSIONAL RELATIONSHIPS AND
FRIENDSHIPS
- PERSONAL GROWTH
GET TO KNOW ALL PARTICIPANTS
BETTER. EVERYONE GETS EDUCATED TO UNDERSTANDING THE PRINCIPLES OF
PARTNERING. SET UP FOCUS GROUPS TO STUDY ISSUES:
- SHOP DRAWING PROCESSING
- PRETASK PLANNING
- SAFETY INCENTIVE PROGRAM
- BUILD IN QUALITY
- SPECIFIC GUIDELINES AND PROCEDURES FOR ISSUE
RESOLUTION. DECIDE HOW OFTEN AND IN WHAT FORM THE CONTINUING
PARTNERING MEETINGS WILL TAKE PLACE.
- NUMBER ONE PRIORITY IS LEARNING THE PARTNERING
PROCESS. THIS IS MY FIRST EXPERIENCE WITH PARTNERING, ALTHOUGH I HAVE
HEARD PEOPLE SING ITS PRAISES FOR YEARS.
- I ALSO EXPECT TO USE THE TOPICS TO SHARPEN MY
PERSONAL MANAGEMENT PRACTICES AND TO DEVELOP NEW TECHNIQUES TO APPLY TO
ALL CURRENT AND FUTURE PROJECTS
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
TO GET TO KNOW ALL THE PLAYERS
THROUGH CONVERSTAION
AND INTERACTION
TO UNDERSTAND WHAT IS IMPORTANT TO EACH PERSON
HERE - WHAT THEY WOULD LIKE TO SEE DURING THE PROJECT
TO DEVELOP AND GAIN TRUST WITH OTHERS
TO FOCUS EVERYONE ON THE COMMON GOAL AT HAND -
A
SAFE, TIMELY, ECONOMICAL, QUALITY PROJECT THAT IS PROFITABLE FOR ALL;
BE
IT MONETARY OR OTHERWISE
MEETING EVERYONE FROM THE DIFFERENT
COMPANIES WHO ARE GOING TO BE ON THE PROJECT
LEARN THE GOALS OF OTHERS
FINDING OUT MORE ABOUT THE AREA
TO GAIN A GOOD WORKING RELATIONSHIP
WITH THE OTHER PEOPLE INVOLVED IN BRINGING THIS PROJECT TO COMPLETION
TO GAIN A BETTER UNDERSTANDING OF MY STRENGTHS
AND WEAKNESSES, AND TO APPLY THAT UNDERSTANDING TO IMPROVING THE WAY
THAT I DEAL WITH AND WORK WITH OTHERS IN BOTH CONFLICT AND AGREEMENT
GET TO KNOW INDIVIDUALS
REPLENISH THE SPIRIT OF PARTNERING
DISCUSS SUCCESSES AND FAILURES OF OTHER
PARTNERING PROJECTS
DEVELOP DISPUTE RESOLUTION TECHNIQUES
IDENTIFY POTENTIAL ISSUES ON THE PROJECT
UNDERSTAND BETTER THE "CONTRACTOR" PERSPECTIVE
OUTLINE PROCESS FOR PARTNERING DURING
CONSTRUCTION
MEETING TEAM PLAYERS AND FINDING
OUT PERSONAL AND SOCIAL ASPECTS ABOUT THEM; THIS OVER AND ABOVE
PROFESSIONAL ASPECTS
START FOUNDATION WORK FOR TRUST AND RESPECT,
BOTH TO AND FROM INTERACTION STANDPOINTS
LEARN AND UNDERSTAND GOALS
SUCCESSFULLY RELAY MY GOALS TO OTHERS
SECURING THE BEST TEAM TO BUILD A
LARGE QUALITY PROJECT ON BUDGET AND SCHEDULE.
TO CONCENTRATE ON QUALITY, SAFETY, SCHEDULE AND
BUDGET
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
GET TO KNOW PROJECT PEOPLE
FIND OUT WHAT CONCERNS ARE
ESTABLISH SOME PROJECT GOALS
GENERATE SOME IDEAS ON HOW TO ADDRESS CONCERNS
AND MEET GOALS
LEARN HOW TO WORK TOGETHER BETTER
- LEARN THE CONCEPTS OF PARTNERING
- MEET AND COME TO KNOW EACH PARTNER
- LEARN HOW TO APPLY PARTNERING CONCEPTS TO THIS
PROJECT
- LEARN TO BE AN EFFECTIVE PARTNER
- FOCUS IN ON TURN AROUND OF SUBMITTALS
- RESOLUTION OF ON-SITE CONFLICTS (LENGTH OF TIME
REQUIRED)
- FORM A WIN-WIN ALLIANCE
- IDENTIFY POTENTIAL PROBLEMS - SOLVE
- GET TO KNOW TEAM MEMBERS
- BUILD TRUST
- LEARN WHAT IS EXPECTED OF US
- LEARNING HOW TO COORDINATE
- DECIDING HOW TO COORDINATE
- LEARN HOW TO WORK WITH OTHERS
- LEARN HOW TO WORK THROUGH CONFLICTS AND
DISAGREEMENTS
- DEVELOP FRIENDSHIPS WITH OTHER TEAM MEMBERS
- HEAR OTHERS’ PARTNERING EXPERIENCES
- WHAT MISTAKES CAN WE AVOID?
- INSTILL PARTNERING AND TEAMWORK IN ALL
PARTICIPANTS
- BE A MOTIVATIONAL EXPERIENCE
- LEARN HOW TO KEEP MOTIVATION LEVEL HIGH
- LEARN HOW TO COORDINATE WORK BETTER WITH OTHER
FIRMS
- TRY NEW IDEAS ON
- GET BETTER UNDERSTANDING OF WHOLE CONSTRUCTION
PROCESS
- ESTABLISH TRUST BETWEEN ALL PEOPLE ON PROJECT
- QUALITY WORK
- GOOD COMMUNICATION
- NEW FRIENDS
- ESTABLISH A MEANS FOR EFFECTIVE DECISION MAKING
AND PLANNING
- GET TO KNOW OTHER MEMBERS OF PROJECT TEAMS
- UNDERSTAND CONCERNS/ISSUES OF OTHER TEM MEMBERS
- LEARN MORE ABOUT PARTNERING PROCESS
- GET "SOMETHING" TO HELP PROJECT GET STARTED ON
THE RIGHT FOOT
- DEVELOP FOCUS ON THE FIRST PART OF THE JOB
- GET SOMETHING DONE
- GET TO KNOW OTHER PROJECT PARTICIPANTS
- DEVELOP IDEAS ON HOW TO WORK EFFECTIVELY
TOGETHER
- LEARN HOW PARTNERING WORKS - WHAT DOESN’T
(HASN’T) WORKED
- UNDERSTAND INDIVIDUAL WORK PHILOSOPHIES
- DEVELOP TRUST
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
- ESTABLISH COMMUNICATIONS WITH PERSONNEL
INVOLVED IN THE PROJECT
- LEARN THE "HOW TO" OF WHAT PARTNERING MEANS
- MEET NEW PEOPLE
- EXPAND MY HORIZONS ABOUT HOW TO LOOK AT
CONTRACTING BUSINESS FROM NEW ANGLES
- GET TO KNOW EVERYONE AND DEVELOP CONFIDENCE IN
TEAM MEMBERS
- DEVELOP TEAMWORK
- START RELATIONSHIPS ON A GOOD NOTE
- LEARN PERSONALITIES
- GET TO KNOW MEMBERS OF THE PROJECT TEAM FROM
OTHER COMPANIES
- BEGIN TO DEVELOP RELATIONSHIPS OF TRUST BETWEEN
TEAM MEMBERS
- LEARN THE EXPECTATIONS OF OTHER TEAM MEMBERS
- I WANT TO HEAR WHAT OTHER PERSONS' THOUGHTS AND
IDEAS ARE FOR THIS PROJECT
- WANT TO KNOW WHAT HAS AND HAS NOT WORKED FOR
THESE PEOPLE IN THE PAST
- WANT TO GET TO KNOW THE PEOPLE I WILL BE
WORKING
WITH
- TO MEET AND BETTER GET TO KNOW TEAM MEMBERS
- TO CONVEY TO THE TEAM THE COMMITMENT OF THE GWS
TO THIS PROJECT AND CONCEPT
- TO HAVE A GOOD CUP OF COFFEE
- GET TO KNOW PEOPLE OUTSIDE OF TRADITIONAL WORK
SETTING
- UNDERSTAND OTHERS’ EXPECTATIONS AND GOALS
- DEVELOP COMMUNICATIONS
- DETERMINE WAYS TO AVOID/RESOLVE CONFLICT
- BREAK DOWN BOUNDARIES
- INTRODUCE US TO THE OTHER TEAM MEMBERS
- WHAT IS PARTNERING?
- HOW DOES IT WORK?
- MEETING AND KNOWING ALL THE PROJECT MEMBERS
- HOW DO WE SOLVE PROJECT PROBLEMS?
- LEARN SOMETHING ABOUT THE MAJOR PARTICIPANTS IN
THIS PROJECT IN LIGHT OF THE FACT THAT WE WILL HAVE A PROFOUND
INFLUENCE ON EACH OTHERS LIVES FOR THE NEXT 2½ YEARS
- UNDERSTAND GWS’S GOALS AND ASPIRATIONS. SAME
FOR
MHJV AND B&V
- MAKE NEW FRIENDS AND HOPEFULLY LEARN SOME
THINGS
I DIDN’T KNOW
- LEARN ABOUT PARTNERING
- MEET NEW PARTNERS
- BUILD COMMUNICATION
- BUILD COOPERATION
- GET TO KNOW THE PEOPLE INVOLVED
- UNDERSTAND WHAT IS EXPECTED AND TO COMMUNICATE
WHAT I EXPECT
- INVOLVEMENT FROM THE ENGINEER AND THE
CONSTRUCTION MANAGERS
- MEET NEW PEOPLE
- LEARN ABOUT OTHERS’ EXPECTATIONS
- SHARE IDEAS
- BUILD CONSENSUS
- ENJOY THE PROJECT - HAVE FUN
- LAY GROUNDWORK FOR BUILDING TEAMWORK AND TRUST
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
| PARTNERING
IS......(PARTICIPANTS' DEFINITIONS OF
PARTNERING AT THE BEGINNING OF THE WORKSHOP) |
...EMPHASIZING/UTILIZING EACH OTHERS’
STRENGTHS - NOT EXPLOITING WEAKNESSES
...A PROCESS OF WORKING TOGETHER WITH OTHER
PROJECT MEMBERS
WITH UNDERSTANDING AND MUTUAL RESPECT TO COMPLETE THE PROJECT TO THE
BENEFIT
OF ALL TEAM MEMBERS
...DEVELOPING COMMUNICATION BETWEEN OWNERS,
ENGINEERSM ABD CONTRACTORS TO ENSURE SUCCESSFUL COMPLETION OF A PROJECT
WITH A MINIMUM OF CONFLICTS
...UNDERSTANDING THE NEEDS OF ALL INVOLVED IN THE
PARTNERSHIP AND WORKING TOGETHER TO MEET THE NEEDS OF ALL THOSE
INVOLVED. PARTNERING IS A CONCEPT THAT HAS BEEN REVITALIZED TO
ADDRESS THE CONFLICTS RESULTING IN THE CONSTRUCTION INDUSTRY. IT IS AN
ATTEMPT TO CHANGE THE NORMAL PERCEPTION OF OWNER, ENGINEER, AND
CONTRACTOR TO ONE BASED ON HONESTY AND TRUST AND
UNDERSTANDING.
...WORKING AS A TEAM TO COMPLETE THE PROJECT
...WORKING TOGETHER ON SOMEWHAT EQUAL TERMS TO
PRODUCE A COMMON GOAL
...WORKING TOGETHER AS A TEAM BENEFITING FROM THE
TALENTS AND EXPERTISE OF EACH OF THE PARTNERS TO MAKE A PROJECT BETTER
...A FORUM WHERE TRUST AND RESPECT ALLOWS OPEN
COMMUNICATION AND INDIVIDUAL ABILITIES TO BE INCORPORATED TO A COMMON
GOAL FOR ALL PARTIES’ COMMON INTERESTS
...DEVELOPING A TEAM ALL WORKING TOGETHER TAKING
ADVANTAGE OF ITS MEMBERS EXPERIENCE AND TALENTS
....LEARNING HOW TO WORK TOGETHER BETTER
...A GROUP WORKING TOGETHER AS A TEAM TO ACHIEVE
COMMON GOALS AND TO ACHIEVE MUTUAL BENEFITS
...ALL PARTIES COMING TOGETHER IN ONE ACCORD TO
ACCOMPLISH THE CONSTRUCTION ON TIME, PROVIDING A QUALITY PROJECT,
WITHIN BUDGET, CONTARCTORS MAKE THEIR MARGINS, NO LOST-TIME ACCIDENTS,
AND TO HAVE A GOOD TIME DOING IT
...TRUST
...WORKING WITH OTHERS TO ACCOMPLISH A PROJECT BY
ALLOWING EVERYONE TO ENJOY THE PROCESS AND NOT DREAD THE WORK EXPERIENCE
...WORKING TO REDUCE ADVERSARIAL TENDENCIES BY
COORDINATING WORK AND BETTER UNDERSTANDING THE OTHER COMPONENTS OF A
PROJECT
...THE ABILITY TO COMMUNICATE, MAKE DECISONS AND
SOLVE PROBLEMS AS A TEAM TO CREATE A QUALITY PROJECT ON TIME AND WITHIN
BUDGET
FOR THE GOOD OF ALL PARTIES INVOLVED
...UNDERSTANDING HOW TO WORK SUCCESSFULLY AS A
TEAM, AND DOING SO
...LISTENING; BEING LISTENED TO;
COOPERATION; FRIENDLY
DISAGREEMENT WITH EFFECTIVE, TIMELY RESOLUTION
...THE DEVELOPMENT OF THE TEAM EFFORT TO CONSTRUCT
A PROJECT EFFICIENTLY
...TEAMWORK
...DOING THINGS THE WAY YOU SHOULD, ANYWAY
...WORKING TOGETHER TO ACHIEVE A COMMON GOAL
...WORKING TOGETHER TO ACHIEVE INDIVIDUAL AND TEAM
GOALS. PARTNERING IS (OR SHOULD BE) HAVING SOME FUN WHILE DOING
IT.
...LABORING TOGETHER TOWARD ONE COMMON GOAL
...WORKING TOGETHER TO ACHIEVE GOALS THAT
OTHERWISE COULD
BE MUTUALLY EXCLUSIVE
...DEVELOPMENT OF PROFESSIONAL RELATIONSHIPS
BETWEEN ALL PROJECT MEMBERS TO ACHIEVE A SUCCESSFUL PROJECT FOR ALL
...A VEHICLE TO ACHIEVE MUTUAL SUCCESS OF A
PROJECT IN
A MANNER THAT THE PARTICIPANTS CAN ACHIEVE THEIR INDIVIDUAL GOALS, BUT,
NOT
AT THE EXPENSE OF THE TEAM
...PEOPLE WITH DIFFERENT PERSPECTIVES WORKING
TOGETHER TOWARD A COMMON GOAL
...DOING BUSINESS WITH THOSE YOU TRUST AND,
EXHIBIT TRUSTWORTHINESS
TO OTHERS
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
|
PROJECT ISSUES
AND OPPORTUNITIES
|
1 - PARTNERING / COMMUNICATION ISSUES
- APPOINTMENT OF PARTNERING CHAMPIONS
- DEVELOP TEAM ENVIRONMENT WHERE ALL MEMBERS ARE
PARTNERS
- UNDERSTANDING EACH CONTRACTOR’S PART OF THE
PROJECT AND ANY SPECIAL NEEDS THEY MAY HAVE
- PLAN FOR MONITORING / EVALUATING HEALTH OF
PARTNERING AND INTEGRATION OF NEW MEMBERS
- RESOLUTION OF CO-OBLIGEE BOND ISSUES
- MINIMIZE PAPERWORK
- HIGHLIGHT POSSIBLE PROBLEM AREAS
- WOW BEST TO COMPLETE MORGAN’S CONTRACT
OBLIGATIONS
- IDENTIFY WHAT IS IMPORTANT TO THE SEPARATE
ORGANIZATIONS AND INDIVIDUALS
- HOW CAN MORGAN BENEFIT THE TEAM OVER THE
DURATION OF THE PROJECT?
- MAINTAIN GOOD LEVEL OF COMMUNICATION BETWEEN
CONTRACTORS
- UNDERSTANDING INDIVIDUAL CONTRACTORS’ WORK
ETHICS
- DEVELOP INCENTIVE PROGRAM FOR ATTENDANCE,
QUALITY, SAFETY, SCHEDULE
- PROBLEMS WITH SUBCONTRACTORS OR SUPPLIERS
2 - SCHEDULE ISSUES
- JUMP-START PROJECT
- HOW TO HAVE AN EFFECTIVE CPM TOOL?
- UNDERSTAND EACH OTHERS’ ROLES AS IMPACT SCHEDULE
- WEATHER IMPACTS TO SCHEDULE
3 - STARTUP ISSUES
- PLAN FOR INTEGRATION OF OPERATIONS OF OLD PLANT
INTO NEW PLANT - SEPARATE SCHEDULE?
- EFFECTIVE SHAKEDOWN, STARTUP, AND HANDOFF TO
OPERATIONS
- GOOD, EFFICIENT, WORKABLE O&M MANUALS AND
EARLY SUBMITTAL
- DETERMINE DHEC REQUIREMENTS FOR STARTUP
- COORDINATE MANUFACTURERS’ STARTUPS AND ON-SITE
VISITS
- DEVELOP TOTAL PROJECT STARTUP PLAN
4 - QUALITY ISSUES
- FIND GOOD SUPPLY OF SKILLED LABOR AND KEEP THEM
- BUILT-IN QUALITY PLAN – NOW
- DEVELOP PRE-TASK PLANNING PROCEDURES
- DEVELOP PROCEDURE FOR WORKING WITH LOCAL
BUILDING INSPECTOR
- MINIMIZE PUNCHLIST
- PLAN FOR INSTILLING WORKER OWNERSHIP
- ACCURATE "AS BUILTS"
- CONSTRUCTION OF WATERTIGHT CONCRETE STRUCTURES
- DEVELOP PROGRAM FOR PROPER RECEIVING AND
STORAGE
OF EQUIPMENT / MATERIALS
5 - SAFETY ISSUES
- ACHIEVE ZERO INJURIES / ZERO ACCIDENTS
- DEVELOP PRE-TASK PLANNING PROCEDURES
- EFFECTIVE HAZARD IDENTIFICATION PROGRAM
- DEVELOP PLAN TO ENSURE VENDORS AND SUBS AGREE
TO
SAME LEVEL OF SAFETY AS AGREED TO BY TEAM MEMBERS
6 - SUBMITTALS/RFI’s/SHOP DRAWINGS
- REQUESTS FOR ALTERNATIVES OR DEVIATIONS
- WORK OUT PROBLEM PROVIDING VFDs FROM SINGLE
SOURCE
- EARLY IDENTIFICATION AND ADDRESS "GRAY" AREAS
IN
DOCUMENTS
- ENSURE COMPLETION OF PRODUCT SUBMITTAL AND
REVIEW PROCESS
- PLAN FOR SHARING SHOP DRAWINGS AND SUBMITTALS
AMONG CONTRACTORS AND SUBS
- BE FLAT ON CONCRETE MIX DESIGN WITHIN 30 DAYS
- DEVELOP A PROCESS FOR EARLY COMPLETION OF
SUBMITTALS
- DEVELOP PLAN FOR STREAMLINING RFI’s
·
7 - ISSUE RESOLUTION
- ISSUE RESOLUTION
- COST ISSUES AND COST CHANGES
- ZERO LITIGATION / ARBITRATION – HOW?
- VALUE ENGINEERING
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
|
ACTION PLANS
DEVELOPED BY SMALL GROUP TEAMS
|
ISSUE: APPOINTMENT OF PARTNERING CHAMPIONS
ACTION: BILL WILL ASK EACH NEW PARTNER TO
APPOINT A CHAMPION
|
ORGANIZATION
|
CHAMPION
|
|
OWNER/GWS
|
LYNN STOVALL
|
|
BEERS
|
MIKE HOLT
|
|
BLACK & VEATCH
|
ANDY PETKASH
|
|
MORTENSON
|
DAN VERTANEN
|
|
MORGAN
|
TIM HALLIGAN
|
|
CROM
|
LARS BALCK
|
|
GOODWATER
|
RICK GALLOWAY
|
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
OPPORTUNITY: DEVELOP TEAM ENVIRONMENT WHERE
ALL MEMBERS ARE PARTNERS
ANALYSIS:
- LACK OF COMMUNICATION
- LACK OF COMMITMENT
- DIFFERENT EXPECTATIONS
- DIFFERENT FIRMS
- LACK OF INCENTIVE
- DIFFERENT LOCATIONS
- LACK OF TRUST
- LACK OF TIME
POTENTIAL SOLUTIONS:
A. DEVELOP TEAM SOLUTIONS
- INCLUDE PARTNERING IN ORIENTATION FOR EACH
ORGANIZATION AND CRAFTSMAN – TC & CM
- PARTNERING SECOND ITEM ON WEEKLY AGENDA:
EXPECTATIONS; HOW ARE WE DOING? SAFETY, SCHEDULE, IOA, PARTNERING
LOGO – BJ
- EMPOWER INDIVIDUALS TO SOLVE PROBLEMS AT LOWEST
LEVEL -- ALL
- FOCUS ON THE GOOD (FRANK) COMMUNICATIONS AND
LISTENING SKILLS -- ALL
- FOLLOWUP PARTNERING MEETINGS INCLUDING
QUARTERLY
MEETINGS OF CHAMPIONS, MONTHLY MEETINGS OF PMs – LYNN / PM / BJ
- EVALUATION OF PARTNERING PROGRAM (3 MONTH
SCORECARD) – CM
- PMs MONITOR PULSE OF PARTNERING PROCESS – TC
& CM
- FORM PARTNERING SUBGROUPS – BJ / PM
- MONTHLY PARTNERING AWARD
- BILLBOARD – SAFETY, SCHEDULE, AGREEMENT
B. MORGAN
- EXIT EVALUATION OF PARTNERING (PM DEVELOP FORM)
–
TC/CM
- CM, MORGAN, BEERS MEET TO DISCUSS TRANSITION
2/11/97 – PMs
ISSUE: DEVELOP INCENTIVE PROGRAM (SAFETY,
SCHEDULE, ATTENDANCE)
ACTION: BJ FORM COMMITTEE OF PMs, SUPT,
FORMEN TO DEVELOP PROGRAM (2 MONTHS)
ISSUE: HOW TO MINIMIZE PAPERWORK
SOLUTION:
- DOCUMENT
- DON’T POSTURE
- ELECTRONIC COMMUNICATIONS (LOTUS NOTES) NETWORK
ISSUE: RESOLUTION OF ISSUES
SOLUTIONS:
- LOWEST LEVEL THROUGH EMPOWERMENT
- REDUCE ISSUES BY PLANNING AHEAD
- PRE-TASK MEETINGS
- GATHER COMPLETE INFORMATION
- BRING SOLUTIONS, NOT JUST PROBLEM
- MOMENTUM TREE
ISSUE RESOLUTION LADDER
|
DECISION MAKING LEVEL
|
CONTRACTOR
|
MORTENSON
|
BLACK & VEATCH
|
GWS
|
TARGET TIME
|
|
FIELD
|
FOREMAN
ASST SUPT
SUPT
|
SUPT (JR)
|
RESIDENT ENGINEER INSPECTOR
|
MIKE
|
1 DAY
|
|
ENGINEER
|
OE
PE
|
PE
M/E
|
PE
STAFF ENGR
RE
|
MIKE
|
5 DAYS
|
|
MANAGEMENT
|
PM
|
PM
|
PM
|
MIKE
|
5 DAYS
|
|
EXECUTIVE
|
GP
VP
|
VP
|
AP
|
LYNN
|
5 DAYS
|
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
ISSUE: HOW TO JUMP START PROJECT?
PROPOSED SOLUTIONS:
- IDENTIFY UPFRONT SUBMITTALS THAT WILL AFFECT
START AND GET TEAM TO RUSH. IDENTIFY WHERE THEY WILL BE
CHECKED. MAKE SURE THEY ARE COMPLETE! SUBMIT BY
2/21/97. GAYLEY SET UP MEETING FOR 2/7/97 WITH APPROPRIATE
PARTNERS: DL, DdF, LB, POB, GT
- NEW TRADE CONTRACTORS TO IDENTIFY STARTING
AREAS
ON JOB FOR COMMUNICATION TO MORGAN – 90 DAY LOOK-AHEAD –NTP + 10
DAYS: DL, DdF, LB, JR
- IDENTIFY GRAY AREAS/QUESTIONS AS SOON AS THEY
ARISE AND ADDRESS THRU RFI PROCESS (SPECIFICALLY THOSE RELATED TO KEY
AREAS OF STARTING)
– GAYLEY ARRANGE MEETING FOR 2/18/97 WITH DdF, DL, LB, SD, TW
- TRADE CONTRACTORS TO PROVIDE SITE UTILIZATION
PLANS TO M/H BY 2/7/97 – JR, CW, TW, LB
- BEERS TO HAVE ADMIN STAFF ON BOARD BY
2/21/97 –DdF; SPECTROL TO HAVE ADMIN STAFF ON BOARD BY 2/7/97
- IDENTIFY ANY POSSIBLE VE THAT COULD AFFECT
START-UP OF WORK BY 2/7/97 – DdF, DL
- FIANLIZE / FORMALIZE MANAGEMENT ADMINISTRATION
PLAN (MAP) (COMMUNICATION, DOCUMENTATION, CHANGES, SCHEDULE, ETC) – POB,
JS, MS BY 2/14/97
ISSUE: HOW TO MAKE CPM AN EFFECTIVE TOOL?
ANALYSIS:
- OUT OF SEQUENCE ACTIVITIES
- DETAIL – TOO MUCH / TOO LITTLE
- MANPOWER LOADING
- TERMINOLOGY / UNDERSTANDING SCHEDULE
- INITIAL CREATION OF SCHEDULE
- ANTICIPATE WEATHER IMPACTS
- REPORTING OVERALL SCHEDULE STATUS TO TEAM
- UPDATING SCHEDULE CONSTANTLY
- KEEPING SCHEDULE FLUID FOR ANY MODIFICATIONS
- TIMELY REPORTING OF SCHEDULE ACTIVITIES /
DURATIONS
- COORDINATION BETWEEN TEAMS FOR AN ACCURATE
SCHEDULE FLOW
PROPOSED SOLUTIONS:
- WORK TOGETHER TO CREATE BUY-IN TO SCHEDULE THRU
ENTIRE PROCESS – TEAM EFFORT BY DVH, DdF, JS, LB, DL AT NTP + 30
DAYS
- CONCISE/CLEAR/UNDERSTOOD DESCRIPTIONS – AGREE
ON
BEFOREHAND – TEAM EFFORT BY JS, TW, CW, JR, LB AT NTP + 30
- UPDATE CRITICAL ACTIVITIES MORE THAN MONTHLY –
MINIMIZE PAPER AND WORK FOR THIS – DVH WEEKLY
- USE CPM TO IDENTIFY LATE DATES FOR CRITICAL
SUBMITTAL / PROCUREMENT ACTIVITIES – GET INPUT FROM B&V –
DdF, BW, POB, JS, LB AT NTP + 21 DAYS
- TIMELY AND ACCURATE TURNAROUND OF UPDATES – SET
REGULAR DATES FOR THIS – DVH MONTHLY
- REQUIRE ADJUSTMENTS TO LOGIC AND DURATIONS TO
MAKE SCHEDULE REPRESENT ACTUAL WORK – SET UP PROCESS TO IMPLEMENT THIS
– "FLUIDITY" – PVH AS REQUIRED
- GET FIELD TO BUY INTO CPM AND ASSIST IN UPDATES
AND CREATION – CW, TW, JS, JR, CROM BY NTP + 30 DAYS
- USE CPM TO IDENTIFY MANPOWER / CREW PROBLEMS
AND
POTENTIAL SOLUTIONS – CW, TW, JS, JR, CROM AS REQUIRED
- TEAMWORK!!
ISSUE: WHAT TO DO ABOUT WEATHER IMPACTS?
SYMPTOMS:
LATE FINISH COST
ISSUES REGULATORY
PENALTIES ENGRG/INSP COSTS
SOLUTIONS:
- EVALUATE LOGIC CHANGES THAT CAN RECOVER
SCHEDULE (ie ADDING CREWS, EQUIP, ETC)
- IDENTIFY / REDUCE EXPOSURE BY LOOKING AT
ACTIVITIES vs TIME OF YEAR
- COST BENEFIT ANALYSIS FOR ACCELERATION AS LAST
RESORT
- UTILIZE PARTNERING TECHNIQUES TO RESOLVE ABOVE
ITEMS AS THEY ARISE
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
ISSUE: HOW TO ENSURE AN EFFECTIVE RFI PROCESS?
SYMPTOMS:
- TIMING OF RFIs
- TRACKING OF RFIs
- COMMUNICATION OF RFIs
ANALYSIS OF PROBLEM:
- EVERYONE NOT MADE AWARE OF CHANGES
- NO COMMON NUMBERING SYSTEM
- TIMING
PROPOSED SOLUTIONS:
- REVIEW RFIs AT WEEKLY PROGRESS MEETINGS
- PRIORITIZE / GIVE REQUESTED RESPONSE TIME ON
RFIs (ON FORM)
- STANDARDIZE RFI FORMS / NUMBERING SYSTEM
- PROVIDE ELECTRONIC CONTRACT DRAWING FILES TO
TRADE CONTACTORS / VENDORS
- SUBMIT SEPIAS OR ADDITIONAL COPIES IF
ADDITIONAL
COPIES NEEDED
- INFO ON CENTRAL ELECTRONIC FILE
- MEET TO RESOLVE ON CONCRETE MIX DESIGN ISSUE
ISSUE: HOW TO ENSURE RESPONSIVE SUBMITTAL
PROCESS?
ANALYSIS:
- NUMBER OF COPIES OF SUBMITTALS
- SUBMITTALS / RFCs
- IDENTIFICATION OF WHAT IS NEEDED FOR EACH
SECTION
- COMMUNICATION BETWEEN CONTRACTORS
- SCHEDULING / TIMELINESS
- EXPEDITING CONCRETE MIX DESIGN
PROPOSED SOLUTIONS:
- UPFRONT LOG OF SUBMITTALS
- PRE-SUBMITTAL MEETINGS / COMMUNICATIONS (TRADE
CONTRACTORS, DESIGN ENGINEER, MANUFACTURER)
- LOG / SCHEDULE
- DISTRIBUTION PLAN
- B&V TO CALL IF ONE PIECE IS MISSING
- B&V TO CALL IF RFC ANTICIPATED
IMPLEMENTATION:
|
ACTION |
WHO? |
TIME |
| 1. |
CREATE LOG W/ O&M |
JERRY S. (B&V) |
1 WEEK |
| 2. |
SUBMITTAL SCHEDULE W/ O&M |
CM / TRADE CONTRACTORS |
MARCH 3 |
| 3. |
PLAN PRE-SUBMITTAL MEETING |
GARY/ BILL/ TC |
MARCH 3 |
| 4. |
PRESUBMITTAL COMMUNICATIONS (PHONE &
E-MAIL) TO DETERMINE WHAT IS NEEDED |
CM/ CONTRACTOR/ B&V |
AS NEEDED |
| 5. |
ADVANCE NOTICE PROCEDURES IF PIECES OF
SUBMITTAL MISSING OR IF RFC ANTICIPATED |
B&V |
AS NEEDED |
| 6. |
DISTRIBUTION PLAN (NUMBER OF SUBMITTALS)
>>CM DETERMINE WHAT HE NEEDS
>>ENGR REVIEW AND RESOLVE |
PAUL O'BRIEN
JERRY/ GARY |
FEB 18
1 WEEK |
| 7. |
PROVIDE ELECTRONIC CONTRACT DRAWING FILES TO
TRADE CONTRACTORS
>>CM DETERMINE WHAT TC NEEDS
>>ENGR REVIEW AND RESOLVE |
DEAN D/ PAUL O/
DAVID L/ GARY
|
1 WEEK
1 WEEK
|
| 8. |
INVESTIGATE CENTRAL ELECTRONIC FILE |
GARY / MIKE |
2 WEEKS |
| 9. |
MEETING ON CONCRETE MIX DESIGN |
CM/TC/B&V/SUPPLIER |
FEB 4 |
| 10. |
IDENTIFY SUBMITTALS TO BE REVIEWED BY GWS
(B&V PROVIDE SUBMITTAL LOG TO GWS) |
CAM |
2 WEEKS AFTER RECEIPT OF LOG |
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
ISSUE: DEVELOP PROCEDURE FOR WORKING WITH
LOCAL BUILDING INSPECTOR
IMPLEMENTATION PLAN:
1. INITIAL MEETING 2/15/97 – BILL JACKSON & JOHN
SNITZMIER
2. PAYMENT OF FEES – M/H
3. INSPECTOR’S EXPECTATIONS UNDERSTOOD
4. PRESENT TEAM’S TESTING AND INSPECTION DOCUMENTATION
EXAMPLES BEFORE CONSTRUCTION – JOHN SNITZMIER
5. COORDINATION OF DOCUMENT EXCHANGE – M/H, B&V,
BUILDING INSPECTOR
6. FIRE INSPECTOR CONTACT AND COORDINATION
7. NOTIFICATION OF INSPECTORS, ELECTRICAL AND ELEVATOR
8. CONTRACTOR REPS AT MEETING:
- BEERS – THOMAS WILSON, DEAN DE FRITES
- HENDERSON – DAVID LYTLE, CHRIS
- IVESTER/GOODWATER – DAN BYERS, JR.
- M/H – O’BRIEN
- B&V – JOHN SNITZMIER, SCOTT DEWHIRST
- GWS – MIKE SHARPLES
AT THE MEETING:
1. TO BE DOCUMENTED:
SOIL TESTS, CONCRETE TESTS, PIPE TESTS, ELECTRICAL
TESTS (GROUNDING, MEG TESTS, LIGHTNING PROTECTION), FIRE
SUPPRESSION/DETECTION, HVAC BALANCING, STRUCTURE LEAK TESTS, PAVEMENT
TESTS.
2. NOTIFICATION EXPECTATIONS AND REQUIREMENTS
- CONTACTS
- MINIMUM NOTIFICATION
PROBLEM: NUMBER OF TRADE CONTRACTORS,
EQUIPMENT, ETC. ON A NEW PLANT IN AN EXISTING SYSTEM COMPLICATES
STARTUP PROCEDURE. HOW CAN WE STREAMLINE THIS?
SYMPTOMS:
- TRAINING OF OPERATIONS STAFF
- COORDINATION OF TRADE CONTRACTORS
- BRINGING NEW PLANT ON LINE – TAKING OLD PLANT
OFF LINE
- O&M MANUALS
- MANUFACTURING SERVICES
- WHO HAS WHAT RESPONSIBILITY?
POTENTIAL SOLUTIONS:
- EARLY SUBMITTAL / APPROVAL OF VENDOR O&M
MANUALS. ENSURE SHARING OF INFORMATION BETWEEN TC THRU SUBMITTAL
PROCESS
- IMPLEMENT STARTUP COORDINATOR PROGRAM – TW
NLT 12/31/97
- CLARIFY ROLES / RESPONSIBILITIES AT STARTUP – 8/1/97,
BJ, GT, LS
- GAYLEY CONSOLIDATE LIST OF REQUIRED
MANUFACTURERS’ SERVICES AND INCORPORATE INTO SCHEDULE – TW, DdF,
DL, DVM, JSO, CROM, GW BY 2/14/97
- SET UP GROUP TO PLAN TIE IN OF NEW PLANT TO
EXISTING SYSTEM – DHEC, B&V, GWS, TRADES, BEERS, MS, SD BY
8/31/97
- PLAN AND IMPLEMENT TRAINING PROGRAM FOR GWS
OPERATIONS STAFF – MS, CF, GT NLT 12/31/97
- DETERMINE / COORDINATE DHEC STARTUP
REQUIREMENTS
– SD, GWS, SUP NLT 12/31/97
- DEVELOP AND IMPLEMENT TOTAL SCADA SYSTEM TIE-IN
AND STARTUP PLAN – DL, B&V, MS, TW BY 8/31/97
PROBLEM: HOW TO FIND A GOOD SUPPLY OF
SKILLED LABOR AND KEEP THEM?
SYMPTOMS:
- LOW UNEMPLOYMENT RATE
- LACK OF SKILLED LABOR AVAILABLE
- OUT OF TOWN CONTRACTORS
- SUBSTANCE ABUSE
- SPECIALTY WORK
- LACK OF INCENTIVE PLAN
- HIGH TURNOVER TO OTHER SITE CONTRACTORS
·
SOLUTIONS:
- YORK CONSTRUCTION
- WORD OF MOUTH
- PRIOR WORK RELATIONSHIPS
- INCENTIVES, MONETARY & NON-MONETARY
- SUBCONTRACTING
· IMPLEMENTATION:
- ADVERTISEMENT BY INDIVIDUAL CONTRACTORS -- ALL
- UTILIZE YORK CONSTRUCTION – BEERS
- DEVELOP INCENTIVE PLAN – INDIVIDUAL
CONTRACTORS AND PARTNERING PRINCIPALS
- UTILIZE SCREENING PROCESS – INDIVIDUAL
CONTRACTORS
- SUBCONTRACT WORK – INDIVIDUAL CONTRACTORS
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
PROBLEM: BUILT-IN QUALITY
SYMPTOMS:
- POOR WORKMANSHIP, UNSKILLED LABOR, APATHY
- REWORK
- COST OVERRUNS
- SCHEDULE DELAYS
- FAILURE TO UNDERSTAND /FOLLOW CONTRACT RQMTS
- POOR PLANNING
- POOR ATTITUDE
- DESIGN ERRORS
- POOR COMMUNICATION
- UNTIMELY INSPECTION
- LACK OF SUPERVISION
- LACK OF TRAINING
- SCHEDULE IMPACTS BY OTHER CONTRACTORS
- LACK OF TWO-DAY COMMUNICATION
- LACK OF EMPHASIS ON QUALITY
- INSTRUCTION ON A NEED TO KNOW BASIS
- NOT TAKING THE TIME TO EXPLAIN
- LANGUAGE BARRIERS
SOLUTIONS:
- TRAINING – ON-JOB, APPRENTICESHIP, FORMAL,
COMPANY-SPONSORED
- INCREASE WORKER KNOWLEDGE ON THE JOB / PROCESS
- ENSURE UNDERSTANDING OF TASKS
- USE OF CHECKLISTS & PREJOB PLANNING
- USE OF CONSTRUCTIVE CRITICISM
- COMMON AGREEMENT ON EXPECTATIONS BY USE OF
SAMPLES
- DEVELOPMENT OF COORDINATION DRAWINGS
- DEVELOP SHORT-TERM PLANNING / SCHEDULING
- COMMUNICATE SHORT-TERM PLANNING / SCHEDULING
- ADOPT "DO IT RIGHT THE FIRST TIME"
- MEET SHORT-TERM PLANS, SCHEDULES, GOALS
- EFFECTIVE PROJECT MANAGEMENT
- MINIMIZE EMPLOYEE TURNOVER
- REVIEW DRAWINGS FOR ERRORS AT ALL STAGES
IMPLEMENTATION:
- CONDUCT FOREMEN MEETINGS TO TALK ABOUT
COORDINATION, SAFETY, WORK PLAN
- USE JOB SITE RADIOS
- EACH CONTRACTOR CONDUCT, AS REQD, INDIVIDUAL
TRAINING, TRADE TRAINING, CREW TRAINING
- CREATE, ADOPT, COMMUNICATE AND MEET SHORT-TERM
SCHEDULES. – INPUT FROM INDIVIDUAL CONTRACTORS, M/H PRODUCE
SCHEDULE
- TREAT ALL EMPLOYEES WITH RESPECT; GIVE THEM A
CLEAR UNDERSTANDING OF RQMTS AND EXPECTATIONS; PROVIDE THEM WITH A
MEANS OF EXPRESSING THEIR CONCERNS.
- DEVELOP WRITTEN CHECKLISTS FOR INDIVIDUAL TASKS
– M/H AND INDIVIDUAL CONTRACTORS
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
OPPORTUNITY: ACHIEVEMENT OF ZERO ACCIDENTS
AND INJURIES
SYMPTOMS:
- MISCONCEPTION THAT THE IDEA IS UNREASONABLE
- POOR OR NO PLANNING
- LACK OF EXPERIENCE / TRAINING
- DEFECTIVE OR IMPROPER EQUIPMENT
- CONTROLLING VENDORS, SUPPLIERS, SHORT-TERM SUBS
- BEING IN A HURRY
- LACK OF KNOWLEDGE ABOUT HAZ-COM PROGRAM
- UNAWARE OF RISKS OR SURROUNDING CONDITIONS
- "CAN’T HAPPEN TO ME" ATTITUDE
- POOR HOUSEKEEPING
- HESITANCE OF INDIVIDUAL WORKERS TO "SPEAK UP"
ABOUT UNSAFE CONDITIONS
SOLUTIONS:
- USE EXAMPLES OF OTHER ZERO ACCIDENT PROJECTS
- CONSTANTLY COMMUNICATE SAFETY GOALS AND
PRINCIPLES
- CONDUCT SAFETY ORIENTATIONS FOR EMPLOYEES
- IMPLEMENT "DRUG FREE" POLICY
- CONDUCT REGULAR SAFETY MEETINGS
- DEVELOP & IMPLEMENT PRE-TASK PLANS
- INVESTIGATE, DOCUMENT, & LEARN FROM
ACCIDENTS / NEAR MISSES
- CONDUCT SAFETY INSPECTIONS
- MARCH 5 SAFETY MEETING
- HOURS WORKED vs NUMBER OF ACCIDENTS SIGN
- IDENTIFY ALL ACCIDENTS
- SAFETY INCENTIVE PROGRAM
IMPLEMENTATION:
- EACH CONTRACTOR SHALL DEVELOP A COMPREHENSIVE
DRUG-FREE POLICY / SAFETY PLAN TO BE ADOPTED BY THEIR SUBS, SUPPLIERS,
VENDORS
- ISSUE A LETTER TO ALL VENDORS, SUPPLIERS, SUBS
STATING MINIMUM SITE SAFETY RQMTS.
- ALL VISITORS MUST SIGN IN AT OFFICE
- SAFETY SIGN AT CONSTRUCTION ENTRANCE
- EACH EMPLOYEE WILL TAKE PART IN A COORDINATED
SAFETY ORIENTATION BY THE CM AND TRADE CONTRACTOR
- REVIEW PRE-TASK PLANS ON ALL LEVELS
- DEVELOP A JOB CLEAN-UP PLAN TO ENSURE REGULAR
HOUSEKEEPING
- DEVELOP AN ACCIDENT / NEAR-MISS INVESTIGATION
TEAM INCLUDING MANAGEMENT, FOREMEN, CREW MEMBERS
- REQUEST A VOLUNTARY OSHA INSPECTION
- IMPLEMENT A SITE AUDIT AND DEFICIENCY
CORRECTION
PROGRAM
- IMPLEMENT A STRETCHING PROGRAM
PROBLEM: HOW TO ENSURE ACCURATE AS-BUILTS?
SYMPTOMS:
- UNTIMELY INCLUSIONS
- MISSED CHANGES
- LACK OF COMMUNICATION OF CHANGES BETWEEN TRADES
- NO DIMENSIONS ON AS-BUILTS
SOLUTIONS:
- REAL-TIME CHANGES – CAD SYSTEM IN THE FIELD
- DEDICATED PERSON TO "AS-BUILT" DRAWINGS
- FIELD CHANGE LOG / SUMMARY
- JOB-WIDE UPDATED SET OF DRAWINGS AT CENTRAL
LOCATION
IMPLEMENTATION:
- CENTRALLY LOCATED SET OF UPDATED DRAWINGS AND
FIELD CHANGES – EACH TRADE CONTRACTOR SHALL HAVE A SINGLE
POINT-OF-CONTACT FOR AS-BUILT
INFORMATION
- COMMIT TO AN ACCURATE PICTURE LOG OF
CONSTRUCTION
- ASSIGN STAFF ENGINEERS TO DEVELOP AS-BUILT
UPDATE PLAN
Participants | Expectations | Partnering Is.. | Team Goals | Issues
& Opportunities | Action
Plans | End of Report
What to Look for In a
Partnering Facilitator
| Why Choose CTC?
|
Where We Have Worked
Services We can
Provide
| See Typical Workshop
Minutes| See Typical
Partnering
Charter Agreement
What People Say About
Us |
Workshop Methodology
| Article Partnering
Brings Success
Some of our Clients
| Typical
Project Types |
Contact CTC
Meet Pete Root
peteroot@ctc-usa.net
Copyright © 2001 - Collaborative Training
Consultants